With the passage of CPUC Resolution E-5252 on April 27, 2023, the Commission established the Transmission Project Review (TPR) Process for the state’s investor-owned electric utilities (IOUs) beginning January 1, 2024. The purpose of the TPR Process is to have a uniform process to review IOUs’ FERC jurisdictional capital transmission projects, allowing the CPUC and Stakeholders to receive robust data from Transmission Owners, and to inquire about and provide feedback on the IOUs’ historical, current, and forecast transmission projects.

The TPR Process provides useful information to numerous programs and proceedings at the CPUC. These include: California Environmental Quality Act (“CEQA”) review and permitting, Integrated Resource Planning (“IRP”), the Distributed Energy Resources (“DER”) Action Plan, General Rate Cases (“GRC”), wildfire mitigation and recovery efforts, and the CPUC’s Risk-Based Decision-Making Framework (“RDF”) and Risk Assessment & Mitigation Phase (“RAMP”).

 

Pacific Gas and Electric

Pacific Gas and Electric (PG&E) ended its previous cycle on October 7, 2026. PG&E directs Stakeholders to its website for all publicly available documents and data releases, listed under the case name "Transmission Project Review (TPR) Process [Res.E-5252]." This also includes a non-disclosure agreement (NDA) that eligible Stakeholders can submit to access PG&E’s confidential data. Please direct all PG&E-specific comments and questions, including NDA submissions, totprprocess@pge.com.

Please see the table below for the schedule of PG&E’s next TPR Process cycle:

PG&E TPR Process Schedule: November 2026 – April 2027 (UPDATED 10/16/26)

EVENT

DATE

Data released

November 2

Date by which Stakeholders provide questions and comments

December 15

Last written responses to Stakeholder questions and comments

January 13

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

January 20

Stakeholder Meeting

February 4

Stakeholders’ questions and comments related to Stakeholder Meeting

February 19

Last written responses to questions and comments related to Stakeholder Meeting

March 15

Last day for Stakeholders to submit project-specific, follow-up questions

March 19

Last written responses to Stakeholder project-specific follow-up questions*

April 2

Last day for Stakeholders to submit comments. There is no expectation of written responses**

April 5

 

Southern California Edison

Southern California Edison (SCE) began its current cycle on June 1, 2026, with the release of its June 2026 TPR Process Project Spreadsheet. SCE directs Stakeholders to its website for all publicly available documents and data releases, listed under the drop-down menu for “2026.” Requests to receive and submit a non-disclosure agreement (NDA) for eligible Stakeholders can be directed to ferccaseadmin@sce.com.

Please see the table below for the schedule of SCE’s current TPR Process cycle:

SCE TPR Process Schedule: June 2026 – November 2026 (UPDATED 10/16/26)

EVENT

DATE

Data released

June 1

Date by which Stakeholders provide questions and comments

July 16

Last written responses to Stakeholder questions and comments

August 6

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

August 14

Stakeholder Meeting

August 28

Stakeholders’ questions and comments related to Stakeholder Meeting

September 11

Last written responses to questions and comments related to Stakeholder Meeting

October 2

Last day for Stakeholders to submit project-specific, follow-up questions

October 9

Last written responses to Stakeholder project-specific follow-up questions

October 23

Last day for Stakeholders to submit comments. There is no expectation of written responses.

October 30

 

San Diego Gas & Electric

San Diego Gas & Electric (SDG&E) began its current TPR cycle on July 1, 2026. SDG&E has created a TPR Process-specific webpage where relevant information can be found. This includes the public version of the data and instructions on how eligible Stakeholders can execute a non-disclosure agreement (NDA) to access SDG&E’s confidential data. Please direct all SDG&E-specific comments and questions, including NDA-related matters, to Kris Bourbois (kbourbois@sdge.com).

Please see the table below for the schedule of SDG&E’s current TPR Process cycle:

SDG&E TPR Process Schedule: July 2026-December 2026 (UPDATED 10/16/26)

EVENT

DATE

Data released

July 1

Date by which Stakeholders provide questions and comments

August 14

Last written responses to Stakeholder questions and comments

September 4

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

September 14

Stakeholder Meeting

September 29

Stakeholders’ questions and comments related to Stakeholder Meeting

October 12

Last written responses to questions and comments related to Stakeholder Meeting

November 2

Last day for Stakeholders to submit project-specific, follow-up questions

November 6

Last written responses to Stakeholder project-specific follow-up questions

November 23

Last day for Stakeholders to submit comments. There is no expectation of written responses.

December 4

 

Please check this webpage for future updates and reach out to Energy Division with any questions about the TPR Process at TPRProcess@cpuc.ca.gov.